Which projects are “subject” to PPP investments?

After a period of consultation, acquisition, and revision, recently at the 9th Session of the 14th National Assembly, the Law on Investment under the public-private partnership method (PPP Law) has been passed, ensuring specificity, of PPP investment, creating a more stable legal environment for PPP projects in the coming time.

The PPP Law just passed by the National Assembly on June 18, 2020

Cancel BT contract

Previously, in Decree 63/2018/ND-CP, the PPP investment method between state agencies and investors (investors), enterprises consisted of 7 types of project contracts. However, the PPP Law just passed by the National Assembly on June 18, 2020, has abolished the BT contract. Thus, the PPP Law only stipulates 6 types of contracts, including BOT (Build - Operate - Transfer), BTO (Build - Transfer - Operate), and BOO (Build - Own - Operate), BTL Contract (Build - Transfer - Lease), BLT Contract (Build – Lease - Transfer), O&M Contract (Operation & Management).

The explanation behind dropping the BT contract is on the ground that after some time, the BT project has left numerous outcomes, terrible general sentiment, in the circumstance of purchasing costly works and trading modest land and public assets, causing a loss for the state budget.

To solve the problem, the National Assembly also specifies the transition of project implementation applying BT contract type. Accordingly, from the viable date of the PPP Law, new projects that apply BT contracts will be halted; Projects applying BT contracts that have not been endorsed for investment policy will stop implementation from August 15th, 2020; Projects that have not given offering reports or solicitation for the proposition shall be suspended. If the invitation for offer or solicitation for the proposition has been given, the solicitation for offers, demand for recommendations will proceed, and as per guidelines of law at the hour of issuance of offering reports or solicitation for recommendations.

For projects with results of investor selection before the effective date of the PPP Law, the contracting agency is responsible for organizing the negotiation and signing of the contract based on the result of investor selection, the bid dossier, proposal documents, bidding documents, request for proposals and legal regulations at the time of issuance of bidding documents, request for proposals; The project that signed the contract before the viable date of this law will continue to implement the project, pay by the signed BT contract and legal provisions at the time contracting.

Only invest in important and essential areas

The PPP Law clearly defines 5 groups of investment sectors under PPP method, including Transport, power grid, power plants (aside from hydropower plants and the State monopoly cases by the Law. Electricity), irrigation, water supply, drainage and wastewater treatment, waste treatment, health care, education-training and information technology infrastructure. These are significant and basic zones that have been implemented in practice for the past 20 years.

The PPP Law clearly defines 5 groups of investment sectors

Regarding the minimum total investment scale of PPP projects for each sector is regulated: Not less than 200 billion VND for projects in the fields of transportation, power grids, irrigation, and water supply, clean, drainage and wastewater treatment, waste treatment and information technology infrastructure. If it is in an area with troublesome and extremely troublesome socio-economic conditions as indicated by the investment law, it must not be lower than VND 100 billion and not lower than VND 100 billion for projects in the medical sector, health, education - training.

PPP investment is an investment method based on term collaboration between the State and the private sector through the signing and implementation of PPP project contracts to attract private investors to invest in public construction, infrastructure and public products and services that the State has the responsibility to provide. The enactment of a separate law to ensure the specificity of PPP investment creates a more stable legal environment for businesses, avoiding the situation of “borrowing” from the provisions of other laws.

Deputy Minister of Planning and Investment Vu Dai Thang

Additionally, the PPP Law also details the eligibility of investors. Accordingly, not all investors can participate in PPP investment, but only investors who meet the following conditions: Having enrolled for establishment and operation by the competent authority of the country in which the investor is operating. Independent financial accounting, ensuring competition in the selection of investors, not in the process of dissolution, not in the case of bankruptcy as endorsed by law, not in the time prohibited from participating in investment activities under the PPP method. Enterprises of which 100% contract capital is held by the State must have a partnership with investors in the private sector to participate in the bid. Investors established under foreign laws must fulfil market access conditions when participating in bidding for projects in conditional market access industries under the investment law.

Regarding the revenue sharing and reduction mechanism, Article 84 of the PPP Law stipulates the plan for implementing the revenue increase and lessen sharing mechanism: When the actual revenue is 125% higher than the revenue in the financial plan. In the PPP project contract, the investor, the PPP project enterprise shares with the State 50% of the revenue increase between that actual revenue and the revenue at 125% of the revenue in PATC. The State shares with investors, PPP project enterprises 50% of the revenue reduction between the actual revenue and the committed revenue in the contract for a PPP project that satisfies certain conditions. This is considered a new mechanism, particularly significant in the process of implementing PPP projects.

Deputy Minister of Planning and Investment Vu Dai Thang said that the enactment of a separate law to ensure the specificity of PPP investment creates a more stable legal environment for businesses, avoiding the situation of “borrowing” regulations of other laws. Previously, elaborate guidelines for PPP activities were only at the decree level, subject to various laws such as the State Budget Law, Investment Law, Public Investment Law, Environmental Protection Law, Enterprise Law, Land Law, Construction Law, Public Debt Management Law ... The legal framework at the decree level will be unstable, ceaselessly adjusted, causing numerous inconveniences for both the State and enterprises when implementing PPP projects with largescale and long-term investment.

EVFTA and opportunities for Vietnam's import & export

Time 22/06/2020 at 14:51

EVFTA - the European Parliament adopted the EU – Vietnam Free Trade Agreement is the latest FTA in Vietnam history in terms of Vietnam’s direct economic benefits. According to the World Bank’s estimation, the impact of this agreement on GDP growth will be 3 times compared to CPTPP (Comprehensive and Progressive Agreement for Trans-Pacific Partnership). Particularly for logistics, what benefits EVFTA will bring to this major?

Navy Hotel Group: An outstanding experience of space and service

Time 16/09/2020 at 09:38

With various forms of hotels and resorts as coastal resort hotels, airport hotels, and city hotels. The chain of Navy Hotel Group has currently been found in popular tourism locations as Dalat, Cam Ranh and Danang. It is expected that a city in HCMC and a coastal hotel resort in Nha Trang will be open at the beginning of 2021.

Fighting against COVID-19: “No socio-economic interruption allowed!”

Time 09/09/2020 at 10:57

In the situation of corona virus strike-back, the Prime Minister asked authorities of various levels, sectors and locales to maintain the double target: fighting against the pandemic and carrying out duties of socioecnonomic developments. “No socio-economic interruption allowed!”

Artisan Nguyen Thi Dung: Pottery a full pasion

Time 16/09/2020 at 08:51

In 20 years working with pottery, with all ups and downs in life, it is the passion that helps Nguyen Thi Dung keep her inspiration and creation. Dung always thinks how to keep pottery art away from dying and how to make it go further to local and foreign pottery art lovers.

DKSH achieved solid results in the unprecedented 2020

Time 15/09/2020 at 14:54

At Group level, in the first six months of 2020, DKSH reported solid results in these unprecedented times. Across markets, DKSH continued to reliably supply products and played a critical role in responding to the pandemic. In Vietnam, DKSH also performed remarkably well, attaining slightly better levels than in 2019. This is a great achievement and a testament to our robust business model and strongly committed workforce, who have really stepped up in these challenging circumstances.

A dispute on new for old insurance

Time 15/09/2020 at 10:11

The damaged property could be replaced under the insurance contract, but the method was not as simple as the thought of the insured in the dispute below, resulting in the lost of hundreds of millions of VND, which was a lesson learned for the enterprise participating in insurance and let readers refer in their practical activities.